Track the Project Timeline - Aylesbury Phase 2B
Aylesbury Phase 2B logoAylesbury Phase 2B

Milestones

The regeneration of the Aylesbury area will take place over a period of around 30 years. A number of sites have already been completed, with many others, including Phase 2B to be completed in the coming years.
  • Stage 1: Introducing the Project

    July 2021

     

    -

     

    August 2021

    Pop-ups, Stakeholder one to ones, Commonplace website, Youth workshops
  • Stage 2: Concept Plans

    September 2021

     

    -

     

    December 2021

    Online exhibition, Drop-in exhibition, Theme workshops, Schools engagement
  • Stage 3: Revised Plans

    January 2022

     

    -

     

    March 2022

    Drop-in exhibition, Presentations
  • Planning application submitted

    May 2022

     

    -

     

    In Progress

  • Statutory consultation period

    July 2022

     

    -

     

    Upcoming

    Statement of community involvement, Ongoing resident involvement
  • Planning committee considers application

    Autumn 2022

     

    -

     

    Upcoming

  • Construction starts on site

    2023

     

    -

     

    Upcoming

    Construction liaison, Ongoing resident involvement
  • First homes ready

    2025

     

    -

     

    Upcoming